Minnesota Electrician License: Requirements, Exam and How to Apply
Here’s what you need for a journeyworker, master or electrical contractor license in Minnesota: required experience, the open-book exam, reciprocity, and the 16 hours of CE that renewal takes.
Last updated October 27, 2026 from Minnesota Department of Labor and Industry requirements
Exam time
5.5 hrs
For the Class A Journeyworker exam
Time to get license
~4 yrs
Journeyworker takes 48 months of experience
Continuing ed
16 hrs
Due before every renewal
Do you need a Minnesota electrician license?
It does. In Minnesota, electricians need a license before they bid or do any work. The business needs a contractor license, and every person doing the work needs a personal electrician license too.
You need the license when
- You install, repair, alter or supervise electrical wiring, equipment or apparatus
- You place bids on electrical work
- As a business, you do or offer to do electrical work, paid or not (contractor license)
- You lay out or plan electrical work (master license)
Exceptions
- We couldn’t confirm specific exemptions, such as work by homeowners
- Minnesota Statutes chapter 326B sets the exemptions, so read it before counting on one
What happens if you work unlicensed
We couldn’t confirm penalty amounts. If you bid or work without the license you need, the Department of Labor and Industry can take enforcement action. Holding only a contractor license doesn’t allow you to do or supervise the work.
How to get a Minnesota electrician license in 6 steps
- Get your experience 48–60 months
You need a minimum of 48 months (journeyworker) or 60 months (master) in the required mix of work. Up to 1 year can come from a board-approved 2-year electrical course. - Send your application to DLI Before the exam
Send in a completed application, signed and notarized, along with the fees. For help, call 651-284-5012 or see the DLI licensing page. - Wait for your approval letter Pre-approval
The Department lets you know when you’re cleared for the exam. Until then, you can’t book it. - Book your exam Online
Use the state’s exam scheduling site to pick a date. Testing centers are located in the larger cities statewide. - Pass the exam Exam day
For the Class A Journeyworker exam, you get 5.5 hours for 80 open-book questions and need 70%. The code book is supplied by the testing agency. - Apply for the license After you pass
A letter will arrive explaining how to apply for the actual license.
Minnesota electrician application checklist
Minnesota application at a glance
- Documented experience: 48 months (journeyworker) or 60 months (master)
- A signed, notarized application with fees
- The state’s approval letter before you book
- Exam scheduled on the state’s booking site
- A printed copy of the 326B electrical laws and rules
- Contractors: insurance certificates, a bond and a responsible master
Minnesota electrician license classes
Personal licenses in Minnesota come in Class A (all electrical work) and Class B (limited work). A business also needs an electrical contractor license, with a licensed master serving as its responsible individual.
A-JRY Most common
Class A Journeyworker
Does and supervises all electrical work, other than planning or laying it out.
| Exam | Class A Journeyworker exam |
| Limit | Can’t plan or lay out work |
B-JRY Limited
Class B Journeyworker
Limited to farms and to single-family homes in towns of under 2,500 people, on single-phase systems no bigger than 200 amps.
| Exam | Not stated |
| Limit | 200 A single-phase |
A-MST Highest personal license
Class A Master
Does and supervises all electrical work, planning and layout included.
| Exam | Class A Master exam |
| Limit | Any electrical work |
B-MST Limited
Class B Master
Can plan and oversee work on farms or single-family homes in towns of under 2,500 people, on single-phase systems up to 200 amps. None issued since 1985, though current holders may renew.
| Exam | Not stated |
| Limit | 200 A single-phase |
EC Business license
Electrical Contractor
Does or offers to do electrical work, whether paid or not. On its own, it doesn’t allow you to perform the work.
| Exam | Not stated |
| Limit | Requires a responsible master |
Requirements for each Minnesota electrician class
You earn a personal license through documented months of experience plus an exam. The contractor license focuses on the business: registration, a bond, insurance and a licensed master who’s responsible for the work.
| Requirement | Journeyworker | Master | Contractor |
|---|---|---|---|
| Experience | 48 months | 60 months | The business doesn’t need it |
| Installation experience | 24–48 months of wiring and installing | 12–48 months of wiring and installing | Not stated |
| Other creditable work | Process control (12), technology circuits or elevators (6), line work (3), maintenance (24 mo max) | Time spent planning, laying out and supervising (12 months max for each) | Not stated |
| School credit | A board-approved 2-year post-high school electrical course can count for up to 1 year | Not stated | Not stated |
| Application | Signed and notarized, with fees | Not stated | Signed and notarized, with fees |
| Bond and insurance | Not stated | Not stated | Certificates for unemployment, workers’ comp and general liability, plus a surety bond |
| Other | An approval letter before you test | Approval before you test | Owner disclosure, Secretary of State registration, and a responsible master or restricted master |
The Minnesota electrician exam
Minnesota’s electrical exams are open book, and starting July 1, 2026, they’re based on the 2026 NEC. The testing agency hands you the code book on exam day, so get comfortable navigating it beforehand.
Format
Open book
Questions
80 (Class A Journeyworker)
Passing score
70%
Exam vendor
Not stated
Scoring and content
- Class A Journeyworker: 5.5 hours for 80 questions; 70% passes
- It covers theory, tables, communication systems, special equipment, special occupancies, equipment, wiring methods, wiring and protection, and general electrical knowledge
- As of July 1, 2026, it follows the 2026 NEC; the code book comes from the testing agency
- Bring printed copies of Minnesota Statutes 326B.081–326B.085, 326B.091–326B.099 and 326B.31–326B.399 too
- Class A Master exam details: we couldn’t confirm them
Retakes
- Wait time between tries: not stated
- Retaking costs $50 with a new application
- The state must pre-approve you before you book
- Book through the state’s exam website
Books and codes for this exam (open book)
The Minnesota Class A Journeyworker and Master electrical exams are open book and based on the 2026 NEC starting July 1, 2026. The testing agency provides a copy of the code book for use during the exam, so your own copy is for studying.
| Reference | Edition | How it’s used |
|---|---|---|
| NFPA 70: National Electrical Code (NEC) | 2026 | Allowed in exam |
| Minnesota Electrical Laws and Rules (Minn. Stat. 326B.081–326B.085, 326B.091–326B.099 and 326B.31–326B.399) | Not stated | Allowed in exam |
The NEC used in the exam room is supplied by the testing agency.
Prep for the Minnesota electrician exam
Our exam prep course, Total Prep and complete bundle for the Minnesota electrician exam. Prices are coming soon.
Books for this exam
Renewing your Minnesota electrician license
You renew every 2 years, and each renewal requires 16 hours of continuing education first. It costs $53 for journeyworkers and $93 for masters, plus a $20 or $40 late fee if you miss the deadline.
Renewal cycle
Every 2 years
CE hours
16
Renewal fee
$53 for journeyworker / $93 for master
Late penalty
$20 for journeyworker / $40 for master
Minnesota electrician CE
Hours, deadlines, required topics and the renewal steps, in one guide.
Licensed in another state?
Minnesota has master-level agreements with 4 states and journeyworker agreements with 9. We couldn’t confirm which steps each agreement waives, so check with DLI before applying.
Alaska: journeyworker reciprocity
Covers the journeyworker level.
Arkansas: journeyworker reciprocity
Covers the journeyworker level.
Colorado: journeyworker reciprocity
Covers the journeyworker level.
Iowa: journeyworker and master reciprocity
Covers both the master and journeyworker levels.
Montana: journeyworker reciprocity
Covers the journeyworker level.
Nebraska: journeyworker and master reciprocity
Covers both the master and journeyworker levels.
North Dakota: journeyworker and master reciprocity
Covers both the master and journeyworker levels.
South Dakota: journeyworker and master reciprocity
Covers both the master and journeyworker levels.
Wyoming: journeyworker reciprocity
Covers the journeyworker level.
City and county rules in Minnesota
The state issues your license, and it’s good anywhere in Minnesota. The per-job details are still handled by local offices.
What the state handles
- Licenses for journeyworkers, masters and contractors
- Approving and scheduling exams
- Keeping contractor bonds and insurance on file
- The 16 hours of CE needed to renew
What cities and counties handle
- Local permits and inspections (ask your city or county)
- Local business registration, if it applies
The Minnesota agency that licenses electricians
Licensing authority
Minnesota Department of Labor and Industry (DLI)
651-284-5012
What the board does
- Issues licenses for electrical contractors, masters and journeyworkers
- Approves applicants and handles exam scheduling
- Keeps records of contractor bonds, insurance and responsible licensed individuals
- Requires 16 hours of CE ahead of each renewal
Minnesota electrician license: common questions
How long does it take to become a journeyworker electrician in Minnesota?
You need 48 months of experience or more, and 24 to 48 months of it must be wiring and installing. Up to 1 year can come from a board-approved 2-year post-high school electrical course.
What’s the difference between a Class A and Class B electrician license in Minnesota?
With a Class A license, you can do any electrical work. Class B licenses, journeyworker or master, only cover single-phase systems of 200 amps or less, on farms or in single-family homes in towns with fewer than 2,500 people.
How much experience does a Minnesota master electrician license require?
It takes 60 months or more. Of that, 12 to 48 months must be wiring and installing, and the rest includes time planning, laying out and supervising jobs.
Is the Minnesota electrician license exam open book?
It is. For the Class A Journeyworker exam, you get 5.5 hours for 80 questions and need 70%. As of July 1, 2026, it follows the 2026 NEC, and the testing agency supplies the code book.
How many CE hours do Minnesota electricians need to renew?
You need 16 hours of continuing education ahead of each renewal.
Does Minnesota offer electrician license reciprocity?
It does. Its journeyworker agreements are with Alaska, Arkansas, Colorado, Iowa, Montana, Nebraska, North Dakota, South Dakota and Wyoming, and its master agreements are with Iowa, Nebraska, North Dakota and South Dakota.
What does a Minnesota electrical contractor license require?
You need a master or restricted master as the responsible licensed individual, plus a surety bond; certificates for unemployment, workers’ comp and general liability; owner disclosure; and Secretary of State registration.
Where this information comes from
- Minnesota Department of Labor and Industry, Construction Codes and Licensing
- Minnesota DLI, Exam scheduling
- Minnesota Statutes chapter 326B (electrical laws and rules)
- Minnesota DLI, CCLD licensing fee schedule (PDF)
- Minnesota DLI, Personal Electrical License Examination Application (PDF)
- Minnesota DLI, Electrical licensing basics
- Minnesota DLI, Electrical personal license renewal form (PDF)